Update #24 PSE&G Weekly Project Update – Week of September 9, 2024 The Project site is located in the portion of the state-owned parking lot near the New Jersey Department of Labor Building and Division of Taxation Building and adjacent to the helicopter pad. For the safety of employees and the community, the sidewalk and …
Category: Weekly Updates
Sep 02
PSE&G Weekly Project Update – Week of September 2, 2024
Update #23 PSE&G Weekly Project Update – Week of September 2, 2024 The Project site is located in the portion of the state-owned parking lot near the New Jersey Department of Labor Building and Division of Taxation Building and adjacent to the helicopter pad. For the safety of employees and the community, the sidewalk and …
Aug 23
PSE&G Weekly Project Update – Week of August 26, 2024
Update #22 PSE&G Weekly Project Update – Week of August 26, 2024 The Project site is located in the portion of the state-owned parking lot near the New Jersey Department of Labor Building and Division of Taxation Building and adjacent to the helicopter pad. For the safety of employees and the community, the sidewalk and …
Aug 16
PSE&G Weekly Project Update – Week of August 19, 2024
Update #21 PSE&G Weekly Project Update – Week of August 19, 2024 The beginning of excavation has been delayed a week as preparations for the enclosure and freeze wall continued. The new start of excavation is on or about August 21st. The Project site is located in the portion of the state-owned parking lot near …
Aug 09
PSE&G Weekly Project Update – Week of August 12, 2024
Update #20 PSE&G Weekly Project Update – Week of August 12, 2024 A contractor of Public Service Electric and Gas Company (PSE&G) will begin excavation on or about August 15th. The Project site is located in the portion of the state-owned parking lot near the New Jersey Department of Labor Building and Division of Taxation …
Aug 02
PSE&G Weekly Project Update – Week of August 5, 2024
Update #19 PSE&G Weekly Project Update – Week of August 5, 2024 A contractor of Public Service Electric and Gas Company (PSE&G) will continue to mobilize equipment and personnel for the John Fitch Way Project and prepare the site for remediation. The Project site is located in the portion of the state-owned parking lot near …
Jul 26
PSE&G Weekly Project Update – Week of July 29, 2024
Update #18 PSE&G Weekly Project Update – Week of July 29, 2024 A contractor of Public Service Electric and Gas Company (PSE&G) will continue to mobilize equipment and personnel for the John Fitch Way Project and prepare the site for remediation. The Project site is located in the portion of the state-owned parking lot near …
Jul 19
PSE&G Weekly Project Update – Week of July 22, 2024
Update #17 PSE&G Weekly Project Update – Week of July 22, 2024 A contractor of Public Service Electric and Gas Company (PSE&G) will continue to mobilize equipment and personnel for the John Fitch Way Project and prepare the site for remediation. The Project site is located in the portion of the state-owned parking lot near …
Jul 12
PSE&G Weekly Project Update – Week of July 15, 2024
Update #16 PSE&G Weekly Project Update – Week of July 15, 2024 A contractor of Public Service Electric and Gas Company (PSE&G) will continue to mobilize equipment and personnel for the John Fitch Way Project and prepare the site for remediation. The Project site is located in the portion of the state-owned parking lot near …
Jul 03
PSE&G Weekly Project Update – Week of July 8, 2024
Update #15 PSE&G Weekly Project Update – Week of July 8, 2024 A contractor of Public Service Electric and Gas Company (PSE&G) will continue to mobilize equipment and personnel for the John Fitch Way Project and prepare the site for remediation. The Project site is located in the portion of the state-owned parking lot near …