PSE&G Weekly Project Update – Week of September 2, 2024

Update #23

PSE&G Weekly Project Update – Week of September 2, 2024

The Project site is located in the portion of the state-owned parking lot near the New Jersey Department of Labor Building and Division of Taxation Building and adjacent to the helicopter pad. For the safety of employees and the community, the sidewalk and walking path adjacent to Route 29 (Market Street) and at the PSE&G project entrance has been closed. Please use an alternate route.

Weekly updates are posted to the project website: https://jfitchwayproject.com/

Questions? Concerns? Call the Project Information Line at (855) 356-2383 or email us at comments@jfitchwayproject.com.

No work will take place on Monday, September 2nd in observance of the holiday.

Ongoing Monitoring & Mitigation Measures During Remediation

  • Dust suppression and odor controls.
  • Odor assessment walks conducted twice daily.
  • Air monitoring within the enclosure.
  • Perimeter air monitoring.
  • Run enclosure air filtration system.
  • Vibration monitoring between remedial work and the nearest onsite buildings.
  • Trucks carrying impacted soil will be covered and use a wheel wash before exiting site.
  • Soil erosion and sediment controls.
  • Site security 24 hours a day, 7 days a week.

Anticipated Work to be Performed: September 2nd – September 6th         

  • No work on September 2nd in observance of the holiday.
  • Continue excavation and transportation of impacted soil by truck to licensed disposal facilities.
  • Continue to run chiller unit for the first part of the freeze wall. 
  • Continue to install piping for establishing a belowground freeze wall for subsequent areas within the remediation boundary. For more information, https://jfitchwayproject.com/wp-content/uploads/2024/05/freezewall.pdf.

Work Performed: August 26th – August 30th          

  • Continued excavation and transportation of impacted soil by truck to licensed disposal facilities.
  • Constructed cement block configuration outside of the enclosure, between it and the contractors’ trailers, to stage clean fill only. It is anticipated that clean fill will begin to arrive and be staged on or about September 13th.
  • Continued to run chiller unit for the first part of the freeze wall.
  • Continued to install piping for establishing belowground freeze walls. Includes trenching outside of excavation limits.
  • Removed and loaded out asphalt at the northern portion of the site.

Community Outreach 

  • Issue 22nd weekly update and posted it to the project website.
  • City Emergency Responders toured site on August 22nd.
  • Weekly updates emailed to:  NJ Department of Treasury (which in turn distributed to the NJ State Department of Labor, Division of Taxation, Hughes Justice Complex, Office of the Governor); City of Trenton officials; Mercer County Officials; community and neighborhood organizations.

Background: The project will remediate impacts to soil from the operations of a former manufactured gas plant (MGP) operated by a predecessor company of PSE&G in Trenton from the late 1840s to late 1890s. Approximately 100,000 tons of MGP-impacted soil will be excavated. Any infrastructure related to the former MGP operations that remain underground also will be removed. Most of the work will be performed within a temporary sprung structure (i.e., tented enclosure). Excavated soil will be transported to a permitted off-site soil treatment and disposal facility. The excavated areas will be backfilled with certified clean fill and restored to the pre-existing conditions. Groundwater encountered during soil remediation activities will be treated and conveyed off site in accordance with permitting.

The project is anticipated to take approximately 18 months to complete. All work is being performed in cooperation with and under the oversight of the Licensed Site Remediation Professional (LSRP), and in accordance with the requirements and guidance of the New Jersey Department of Environmental Protection (NJDEP).